- Fragmented control of the grid can cause unplanned loop flows, shifting physical and financial strain onto neighboring countries.
- ACER decisions are merging the Core and Italy North CCRs into a single Central Europe Capacity Calculation Region with coordinated flow-based domain.
- Security calculations have moved from national desks to Regional Control Centres.
- The Central Settlement Entity allocates costs for cross-border redispatch with a “polluter-pays” model to trace power flow responsibility.
When a winter gale sweeps across the North Sea, the surge of German wind generation ignores the political borders. After all, power follows the path of least impedance. The resulting unscheduled loop flows spill across the networks of Poland, Czechia, and Austria, causing them to overload their regional substations and clogging transit corridors long before the electricity ever reaches industrial buyers in southern Germany or northern Italy.
Treating these constraints as domestic issues solved by isolated national control rooms is like sticking your head in the sand. When one transmission system operator (TSO) throttles a line or orders emergency redispatch in a vacuum, it only pushes the physical strain - and the financial bill - directly onto its neighbors.
In Part 1 of our grid congestion management series, we examined the software failures that make local redispatch so expensive. Today, we zoom out to the macro-regional level. Managing Europe's crowded electrical airspace requires looking past individual control rooms to understand the mathematical and regulatory reality linking power systems across the continent.
Physics doesn't recognize boundaries
For years, European capacity calculation was carved into artificial administrative zones known as Capacity Calculation Regions (CCRs). The Core CCR covered 12 bidding zones in Central Western and Eastern Europe, while the Italy North CCR governed the Alpine borders with four bidding zones.

While treating the Alps as an administrative firewall made for clean paperwork, it ignored basic electrical behavior. As a matter of fact, power flows across France, Austria, Slovenia, and Italy interact continuously. Simulating available capacity on one side of the mountains while treating the other side as an external boundary created structural blind spots. Operators routinely misjudged cross-border loop flows, forcing them into expensive emergency redispatch when physical lines hit their thermal limits.

Compounding this Alpine puzzle is Switzerland. Geographically, Swissgrid sits physically dead center between Germany, France, Austria, and Italy, yet remains outside the EU internal electricity market coupling. The old Italy North framework relied on static workarounds to account for power crossing the Swiss Northern Borders. Even within a unified Central European calculation domain, Swiss transit flows remain an external physical reality that regional algorithms must continually model around to avoid miscalculating available transmission capacity.

Regulators stepped in to get rid of virtual “hand offs” at the border. Through ACER Decision 04/2024, the agency mandated merging the Core CCR and Italy North CCR into the unified Central Europe (CE) CCR. This consolidated 14 bidding-zone areas into a single flow-based domain, dissolving the artificial boundary between the two regions.
ACER Decision 10/2025 pushed this integration into real-time operations. The mandate extended the merger from Flow-Based Day-Ahead (FBDA) calculations directly into intraday capacity calculations, Regional Operational Security Coordination (ROSC), coordinated Redispatching and Countertrading (RDCT), and unified cost-sharing frameworks.
One shared physical bottleneck now requires one coordinated calculation region.
Regional coordination centers
Unifying 14 bidding zones breaks traditional control room operations. A transmission engineer sitting in Dortmund, Vienna, or Warsaw cannot manually calculate the regional physical impacts of thousands of simultaneous commercial trades.
The security calculations have formally migrated out of national control rooms and into Regional Coordination Centres (RCCs), including Coreso in Brussels and TSCNET in Munich.

RCCs run the optimization engines behind Regional Operational Security Coordination (ROSC). Instead of relying on static safety margins, ROSC algorithms ingest the Common Grid Model (CGM), an hourly digital representation of the entire European high-voltage network.
When the software flags an operational security violation, meaning the grid could become unstable if a major line suddenly trips (the standard N-1 security rule), the regional engine works through a clear sequence:
- Zero-cost topological fixes: The software first scans every available grid configuration across the CE CCR. It assesses whether adjusting phase-shifting transformers (specialized transformers that act as valves to throttle or force flows along specific lines) or splitting electrical paths inside substations to redirect currents can relieve an overload at no commercial cost.
- Cross-border RDCT optimization: If topological switching cannot clear the bottleneck, the platform co-optimizes redispatch and countertrading across borders. Instead of a local operator firing up a costly peaking plant right next to a congested line, the regional engine might order a minor generation drop in France paired with a ramp-up in Austria, resolving the issue at a fraction of the cost.
For commercial market participants and flexibility developers, this consolidation shifts the commercial incentives. A single Central European domain means cross-border redispatch orders will increasingly dictate local asset dispatch schedules and intraday prices, displacing local bilateral TSO phone calls. If an asset sits behind a recurring macro-regional bottleneck, regional security algorithms will increasingly determine its run hours rather than national commercial market clearing.
So solving a constraint in software is straightforward. But deciding who pays for it is a minefield.
Who pays the bill?
When an Austrian hydro plant is instructed to ramp up to relieve a line overload caused by northern German wind heading for Italian industrial demand, allocating the bill becomes complex. Austrian consumers should not absorb the cost of a bottleneck generated by transit power.
Europe applies the polluter-pays principle through coordinated RDCT cost-sharing. To implement this, TSOs break down the power flows moving across congested corridors. Regional algorithms use Power Transfer Distribution Factors (PTDFs) to trace what percentage of an overload stems from domestic schedules versus uncoordinated transit and loop flows from neighboring countries.

The Central Settlement Entity (CSE) manages this financial clearing. The CSE handles hundreds of millions of Euros in cross-border re-invoicing. It takes the physical dispatch data validated by the RCCs, applies ACER-mandated cost-sharing formulas, and settles the balances among all participating operators.
Without automated financial settlement, TSOs end up locked in retroactive audit disputes over whose commercial export overloaded which cross-border transformer.
Managing the latency risk
Migrating security calculations to regional centers introduces a clear technical challenge: operational latency.
If an unexpected line trip or sudden solar ramp occurs, control rooms do not have 45 minutes to wait for a regional optimization loop to re-converge. When regional recommendations arrive too late, operators abandon coordination, pick up the phone, and fall back on crude, localized manual redispatch.
Closing this gap requires event-driven software architectures built specifically for cross-border coordination:
- Streaming grid models: Platforms must ingest Common Grid Models, stream topological switch states, and track market clearing as live events rather than static hourly files.
- Automated asset instruction matching: Software must instantly convert RCC remedial action recommendations into executable asset schedules, verifying that the assigned flexibility providers can ramp within tight intraday deadlines.
- Real-time financial exposure calculation: Control room operators need continuous visibility into the cost implications of each action. Calculation engines must project CSE settlement impacts before an operator confirms a cross-border dispatch instruction.
By linking RCC regional calculations directly to national dispatch desks, modern energy platforms bridge the gap between macro-level network optimization and real-time execution.
Market design exploits
Unifying Central Europe into a coordinated calculation region eliminates the blind spots between national borders. It replaces administrative guesswork with regional physics and manual telephone calls with automated security algorithms.
Yet, as operators shift from emergency administrative orders to transparent, regional, market-based mechanisms for congestion relief, they expose themselves to an entirely different structural vulnerability: behavioral gaming.
When market participants figure out exactly where the grid is constrained, clever bidding strategies can turn physical bottlenecks into private profit centers.
Coming up next in Part 3 of our Grid Congestion Management Series, we tackle the increase-decrease (inc-dec) threat. We will explore how traders exploit the gap between day-ahead clearing and intraday redispatch to deliberately inflate congestion, and look at the market-monitoring tools TSOs use to spot the manipulation before it drains system budgets.
Related insights